| Captive Power
Plant
Captive power plant means
powerplant including generating sets if any installed by consumer of
MP Electricity Board (MPEB) for his own use.
Eligibility For Installation of
Captive Power Plants
- Such
entrepreneur shall be eligible to install captive power plant who
-
- is a
consumer of Electricity Board (High Tension or Low Tension) and-
- does
not owe any arrears/amounts to Electricity Board,
-
In case of
any dispute arising regarding payment of arrears due to MPEB-
- The
concerned consumer shall have to deposit immediately the
principle amount out of the arrears and also simple interest @
18% per annum on such amount.
- After
depositing the amount as mentioned above, the dispute may be
referred to Divisional Commissioner of concerned area for
arbitration.
- The
consumer shall have to submit an undertaking to MPEB that the
necessary amounts, if any, shall be deposited within 15 days of
the order of the Commissioner.
- The
consumer shall have to deposit the necessary amounts as per the
order of Divisional Commissioner within 15 days of the order.
Use of
Captive Power Plant
The
captive power plant shall have to be used only as following:
- For such consumers, to whom
permission is granted after issue of this notification, it shall
be binding to draw atleast 50% of electricity from MP Electricity
Board out of their total monthly requirement.
- The consumer shall have to
install a high precision electricity meter at his own cost as per
the standards laid by the Board, so that MPEB may record the
reading of power generation from time to time.
Duration
The permission
to run captive power plant shall be given for a period not exceeding
10 years at a time.
Wheeling
-
Wheeling of power shall not be allowed to a consumer installing
captive power plant, other than for his own use.
-
Electrical power generated by captive power plant shall not be
sold to third party.
- In
order to continue or avail the facility of wheeling for own use,
all the arrears shall have to be paid by the consumer to MPEB.
- The
consumer availing the facility of wheeling shall have to pay the
reactive power charges regularly, as applicable from time to time.
Wheeling Charges
The facility of wheeling shall be
available to the consumers installing captive power plant for his
own use subject to payment of the following charges.
|
S.No.
|
Particular
|
Wheeling Charges
|
|
Upto15MW
|
Above15MW
|
|
1.
|
Percentage of quantum of electricity supplied upto a distance
of 40 KM
|
7%
|
10%
|
|
2.
|
Percentage of quantum of electricity supplied upto a
distance of 60 KM
|
9%
|
12%
|
|
3.
|
Percentage of quantum of electricity supplied upto a distance
of 100%
|
|
15%
|
|
4.
|
Percentage of quantum of electricity supplied above a
distance of 100 KM
|
13%
|
17%
|
In case where
wheeling is done to more than one unit of consumer, the wheeling
charges shall be calculated on the basis of the concerned slab of
total wheeled power.
Energy
Banking
The facility of
energy banking shall not be available to any consumer/entrepreneur.
Exemption From Electricity Duty
No exemption
shall be available on the electrical energy generated by any captive
power plant. However, the existing exemption shall continue for such
period as may be fall short of total period of exemption granted
earlier. If any consumer has availed the benefit of exemption of
electricity duty once, then the exemption shall stand withdrawn in
case of replacement of captive power plant.
Cess on Electrical Generated by
Captive Power Plant
An energy
development cess shall be levied @ 20 paisa per unit from captive
power plant. The cess shall be recovered by MPEB alongwtth monthly
electricity duty.
Provision of
Committee Regarding Grant of Consent toCaptive Power
Plant/Generating sets
As per the
existing law, the entrepreneur/consumer has to obtain consent of
Electricity Board for installation of captive power plant under
section 44 of Electricity (Supply) Act, 1948. In this regard, the
consumer of MPEB shall be allowed to apply to the Committee headed
by Principal Secretary (C&l) in case of delay in obtaining consent
or problems related to permission for installation of new captive
power plant. The Principal Secretary (Energy), Chairman/Member
(Finance), MPEB and Managing Director, MPSIDC shall be the members
of this Committee. The Committee shall dispose off the applications
within four weeks.
Statutory and
other Permission
- The
consumer shall have to obtain all statutory/non statutory
permission for installation of captive power plant and shall be
required to make his own arrangements for land, fuel and water
supply.
- If the
capacity of the captive power plant exceeds 25 MW, the consumer is
required to obtain necessary prior permission from Central
Electricity Authority.
Interconnection Line
For
inter-connecting the power supply, from Captive Power Plant to the
grid system of MPEB, if new inter-connection lines, equipments, etc.
are required or the capacity of existing transmission and
distribution lines, etc. is required to be augmented so as to
provide the facility of wheeling, then its cost shall be borne by
the applicant entrepreneur/consumer.
Cancellation
of Permission
If any
entrepreneur/consumer is found to be violating the Captive Power
Policy, terms and conditions imposed by MPEB in the permission
granted, agreement executed regarding electricity supply with MPEB,
etc. then the permission for captive power plant shall be cancelled
and the action shall not be taken against such consumers as per the
existing acts/rules. |